Festival Mall Expansion

Project data

Location: Alabang Muntinlupa City, Philippines

PD8 tableforms provided for 5.2m high beam and slab arrangement

Requirements

  • Limited crane availability and tight time schedule
  • Formwork solution to adapt with strong wind conditions

Customer

Equipment Engineers, Inc.

Customer's benefit

high productivity due to safe and convenient work processes

PERI solution

PD8 Shoring System