South Health Campus, Canada
Project data
Location: Calgary, Canada
Medical centre with 644 beds south of Calgary
200,000 m² floor space
Shell construction time of main building: 2007-2011
(whole campus will be finished in 2018)
Requirements
Special requirements concerning slab dimensions, construction time and construction sequence
Customer
Ellis Don, Calgary, Canada
Customer's benefit
- shuttering of a slab area of 2,800 m² per week
- no shoring measures necessary for the lower storeys
- easy and fast moving process
- special solution saves 30-40% of work time
- only 4 instead of 6 construction cranes
Scott Thompson | Sam Poskovic
Project leader | Foreman
The PERI solution helps us to save 30 - 40 % of work effort so that we are able to work very efficiently. What is more, we only need four instead of the six cranes that were originally planned.
PERI solution
- 57 special tables with 90 m², based on standard components with only 4 corner supports without intermediate supports
- load transfer via existing reinforced concrete columns
- DCS system (deflection compensating system) automatically compensates for the deflections occurring during pouring
- special transportation trolleys for easy and fast manual moving in vertical and horizontal directions