You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.

Motorway Bridge D1, Slovakia

Project data

Location: Považská Bystrica, Slovakia

The “Centrum” motorway junction as a 767-metre-long bridge structure

Construction period: 2008 - 2010

Requirements

  • single and twin-spaced hollow box cross-sections with variable superstructure widths
  • the cross-sections as well as the longitudinal and lateral inclinations change continuously

Customer

Bögl a Krýsl, k.s, Prešov

Customer's benefit

  • cost-effective construction using rentable system components from the VARIOKIT system
  • transfer of vertical and horizontal loads from a height of over 15 m
  • bundling of standards for concentrated load points using PERI UP Flex falsework
Ľuboš Šalváry, Site Manager: Motorway Bridge D1, Považská Bystrica, Slovakia
Ľuboš Šalváry
Site Manager

We have been working together with PERI for many years now, and once again we have not been disappointed. For each bridge section, we received the right formwork and scaffolding solution.

PERI solution

Planning and execution based on rentable modular systems:

  • construction of the hollow box cross-sections for the superstructure was effected with 15-m-high PERI UP falsework
  • the external web formwork and cantilever formwork were created by means of variable raised formwork units using VARIOKIT system components

PERI systems in use